This Week at the Lynnwood Campus

Categories: Church,Move to Lynnwood

It was a week of details at the Lynnwood campus! The Kids rooms’ sinks now have running water (thanks, Crown Plumbing!), some furniture was moved into place, and the staff spent time preparing for our volunteer work party that’s happening on the 18th. Have you signed up yet? Tell us you’re coming!

 

 

 

 

 

 

 

 

 

The Big Stuff Still Remaining:

  • Resurfacing the parking lot (completed!)
  • Replacing the carpet & bathroom flooring downstairs (completed!)
  • Adding electrical outlets to downstairs office space (completed!)
  • Sound system installation & inspection (almost complete!)
  • Finishing fire alarm system & inspection (awaiting inspection)
  • Parking Lot Lights (awaiting inspection)
  • Touch-up Painting
  • Landscaping
  • General inspection for occupancy
  • Packing, Moving, Unpacking, Finishing Touches