This Week at the Lynnwood Campus

Categories: Church

IMG_9621

This week brought more progress in the Kids Area as curtains were hung and temporary sinks were installed. Coming soon are beautiful, custom built cabinets and full-size sinks, but this setup should get us past inspection!

We also compiled a Super Detailed Punch List to help us keep moving forward
while we wait on the bigger things. So, mark your calendars for a big ol’ work party on Saturday, November 18, 9am-12pm. We’ll be hauling stuff out, moving furniture around, and doing lots of cleaning. Kids 10 and older are welcome to work alongside you, but please leave your littles at home (with a grown-up, of course!)

The Big Stuff Still Remaining:

  • Resurfacing the parking lot (completed!)
  • Replacing the carpet & bathroom flooring downstairs (completed!)
  • Adding electrical outlets to downstairs office space (completed!)
  • Sound system installation & inspection (almost complete!)
  • Finishing fire alarm system & inspection (awaiting inspection)
  • Parking Lot Lights (awaiting inspection)
  • Cleaning & Touch-up Painting (cleaning & touch up have begun!)
  • Landscaping
  • General inspection for occupancy
  • Packing, Moving, Unpacking, Finishing Touches