Good stuff happening this week! Most of the effort has been focused in the Big Room.

52649155499__3109C9FB-E5DB-47D3-B499-24F7FF1BA387
Acoustic panels have been installed.

52649582894__3645DF0D-5A49-443D-A5DC-FE819BC468B7
The screen is up, the projectors are being configured, and the sound board is running.

52649474722__1B3598A1-06D2-4427-9A2E-5B8C4EAD1E8F
And here, we see our friend Jeff doing some mudding & sanding in the Kids area! Thanks, Jeff!!

The Big Stuff Still Remaining:

  • Resurfacing the parking lot (in progress – striping & curbing rescheduled for next week)
  • Replacing the carpet & bathroom flooring downstairs (completed!)
  • Sound system installation & inspection (installation nearly complete!)
  • Touch-up Painting
  • Finishing fire alarm system & inspection
  • Landscaping
  • General inspection for occupancy
  • Packing, Moving, Unpacking, Finishing Touches